Please review attachment Lesson 10 Assignment Worksheet Assignment Instructions For this assignment, you will be calculating the expected monetary

Please review attachment

Lesson 10 Assignment Worksheet

Assignment Instructions

For this assignment, you will be calculating the expected monetary value (EMV) for each risk using the information in the following chart:

Risk Register

Risk #

Activity #

Probability

Cost Impact

EMV

1

AA

25%

$8,000

2

BB

70%

$3,800

3

AA

15%

-$3,000

4

DD

60%

$25,000

5

DD

40%

-$18,500

6

AA

65%

-$6,000

7

BB

40%

$7,500

8

BB

35%

$30,000

9

CC

50%

$45,000

10

EE

45%

-$28,750

Type or write your answer in the EMV column. Once you have finished and recorded your calculations, use the completed chart to answer the following questions.

Remember: Positive numbers represent positive risks.

Questions to Answer

How many of the
risks identified are positive?

The total sum of the EMV column represents the potential budget for the contingency reserve. Add up all of your EMV calculations. What is the sum?

Which
activity has the most risks identified?

Some activities have both positive and negative risks identified. Add all risks for each activity. This calculates the net EMV per activity. Which
activity has the highest dollar value for
positive risks?

Some activities have both positive and negative risks identified. Add all risks for each activity to calculate the net EMV per activity. Which
activity has the lowest dollar value for
negative risks?

What is the net EMV for Activity DD?

There are three risks associated with Activity BB. Combine all three risks to determine the net EMV, and interpret the meaning behind the calculation. Is the overall risk value as calculated here positive or negative?

Take a look at Activity EE. Calculate the net EMV, and interpret the meaning behind the calculation. Is the overall risk value positive or negative?

Which
risk has the highest EMV? (Note: This is should be based on the numerical value and could be positive or negative.)

Which
risk has the lowest positive EMV?

11. Every day we encounter the possibility of risks. Some we notice and others go unnoticed. Statistically speaking, the riskiest thing you do is get into your car and drive. Think about some of the daily risks you could potentially encounter in your projects (or just life in general).

Share This Post

Email
WhatsApp
Facebook
Twitter
LinkedIn
Pinterest
Reddit

Order a Similar Paper and get 15% Discount on your First Order

Related Questions

1 Spring 2024 Assessment Brief Managing Performance through People 2 Spring 2024 Managing Performance through

1 Spring 2024 Assessment Brief Managing Performance through People 2 Spring 2024 Managing Performance through People 5HR515 Contents Module Leader …………………………………………………………………………………………………………………. 3 Key dates and details …………………………………………………………………………………………………………. 3 Description of the assessment …………………………………………………………………………………………….. 3 Assessment Content ………………………………………………………………………………………………………….. 4 Assessment Rubric ……………………………………………………………………………………………………………. 5 Anonymous Marking …………………………………………………………………………………………………………. 8 Assessment Regulations …………………………………………………………………………………………………….. 8

Revise to discuss Target stores as a company Assessing Opportunities for Adding Value at Microsoft Rosiland Young University of Phoenix Dr. Louay

Revise to discuss Target stores as a company Assessing Opportunities for Adding Value at Microsoft Rosiland Young University of Phoenix Dr. Louay Chebib Management 576 Introduction Organization Overview Strengths and Weaknesses Assessment of External Environment Opportunities for Adding Value Economic Value Social Value Environmental Value Recommended Opportunity Agenda 2 Description