8/3/2022 By TUY Pheap, OPM Course for MBA, B23, G11 1 Assignment lecture #3 1. Construct an AON network based on the following: ACTIVITY IMMEDIATE

8/3/2022 By TUY Pheap, OPM Course for MBA, B23, G11 1

Assignment lecture #3
1. Construct an AON network based on the following:

ACTIVITY IMMEDIATE PREDECESSOR(S)
A –
B –
C –
D A, B
E C

2. Insert a dummy activity and event to correct the following AOA network:

8/3/2022 By TUY Pheap, OPM Course for MBA, B23, G11 2

Assignment (cont’d)
3. The City Commission of Nashville has decided to build a botanical garden and picnic area in

the heart of the city for the recreation of its citizens. The precedence table for all the
activities required to construct this area successfully is given.

CODE ACTIVITY DESCRIPTION
TIME (IN
HOURS)

IMMEDIATE
PREDECESSOR(S)

A Planning Find location; determine resource requirements 20 None
B Purchasing Requisition of lumber and sand 60 Planning
C Excavation Dig and grade 100 Planning
D Sawing Saw lumber into appropriate sizes 30 Purchasing
E Placement Position lumber in correct locations 20 Sawing, excavation
F Assembly Nail lumber together 10 Placement
G Infill Put sand in and under the equipment 20 Assembly
H Out-fill Put dirt around the equipment 10 Assembly
I Decoration Put grass all over the garden, landscape, paint 30 Infill, out-fill

a) Draw the Gantt chart for the whole construction activity.
b) Draw the AON network for the construction activity.
c) Draw the AOA network for the construction activity.

8/3/2022 By TUY Pheap, OPM Course for MBA, B23, G11 3

Assignment (cont’d)
4. The planning department of an electronics firm has set up the activities for developing and production of a

new MP3 Player. Given the information below, develop a project network using Microsoft Project. Assume a
five-day workweek and the project starts on January 4, 2020.

Activity ID Description Activity Predecessor Activity Time (weeks)

1 Staff None 2
2 Develop market program 1 3
3 Select channels of distribution 1 8
4 Patent 1 12
5 Pilot production 1 4
6 Test market 5 4
7 Ad promotion 2 4
8 Set up for production 4, 6 16

The project team has requested that you create a network for the project, and determine if the project can
be completed in 45 weeks.

Share This Post

Email
WhatsApp
Facebook
Twitter
LinkedIn
Pinterest
Reddit

Order a Similar Paper and get 15% Discount on your First Order

Related Questions

Revise to discuss Target stores as a company Assessing Opportunities for Adding Value at Microsoft Rosiland Young University of Phoenix Dr. Louay

Revise to discuss Target stores as a company Assessing Opportunities for Adding Value at Microsoft Rosiland Young University of Phoenix Dr. Louay Chebib Management 576 Introduction Organization Overview Strengths and Weaknesses Assessment of External Environment Opportunities for Adding Value Economic Value Social Value Environmental Value Recommended Opportunity Agenda 2 Description

Section A Input Data

Section A Input Data EduCredit is the education loan division of a bank. It is considering a batch of applications for student loans repayable in one year. EduCredit charges each loan applicants an annual interest rate that depends on the band of their credit scores (A is the highest) Loan

Homework  Channels and Metrics Note:  At the start of your DQ post,

Homework  Channels and Metrics Note:  At the start of your DQ post, remind us of the company and product/service you have chosen for your marketing campaign. Choose one social media channel and one traditional channel that you plan to use in your marketing campaign. For each channel, answer the following

BUSI46S15 Competitive Strategies & Organisational Fitness

BUSI46S15 Competitive Strategies & Organisational Fitness Postgraduate Programmes 2023/24 SUMMATIVE ASSIGNMENT – BUSI46S15 Competitive Strategies and Organizational Fitness Select an organization, identify its competitive environment (that is, the population it is a member of) [5 marks] Analyse (qualitatively) the ecological and institutional conditions in the population. [10 marks] Provide a